Monday, September 21, 2009

Remodel Wrap Up Day 4-13

We have been super busy with the house and on top of dealing with all of the issues that arise when you are expecting a newborn, that both of us haven't been able to blog. Good news, the project has pressed on.

The wood floors have been completely installed, we are now have (had) to wait for 10 days until they settle and can be scraped and stained. We are currently on day 5, so only 5 more days to go. This past weekend, we pulled out the countertops, sink, cooktop and old trash compactor.

We ordered the appliances Friday and they should be in Wednesday. The countertops are going in Thursday.

Here are the pics from last wednesday, when they were in the midst of installing the wood and had finished grouting the tile.